Fayram, and 2 co-authors, reported in 2020 that the information within this report supports the presence of economic lithium mineralization and
further work on the project. The mineralization occurs within a large lithium-bearing clay deposit. The estimated Mineral Reserves for the project are large and capable of supporting a mine life of more than 40 years.
The project as outlined is based on a production rate of 15,000 tpd. This is identical to the PEA and is selected based on constraints in transportation and market considerations. The capital costs for the project are estimated at $493 million, of which the acid plant is a major component. A lower production rate could be considered as a means of capital cost reduction by deferring purchase of the acid plant and buying sulfuric acid instead; this alternative was not studied.
At the design rate of 15,000 tpd, the project has an estimated production rate of 27,400 tpy LCE. The operation is expected to produce lithium in the form of battery-grade lithium hydroxide. The estimated average operating cost of $16.90/t of material equates to $3,387/tonne LCE. The analysis in this report uses a base price of $9,500/tonne LCE on lithium sales.
The results are an after-tax NPV@8% of $1.030 billion and an after-tax IRR of 25.8%. The results are positive. The project is exposed to risks typical of a mining project at a prefeasibility level of study.